Drone view of the Rose Homes site on Newtown Road, Ramsey, with plots at foundation stage and two slabs poured
Case study: Rose Homes, Ramsey

Groundworks in Ramsey: nine homes for Rose Homes

Groundworks in Ramsey for Rose Homes on Newtown Road: nine plots, made up of two pairs of semis and five detached homes. We excavated every plot, cast the ring beams and concrete foundations, built the substructure blockwork, laid block and beam, and ran the plot drainage, services, foul drainage and storm water. We are main contractor on site.

  • 9plots for Rose Homes
  • 3.5 mdeep road sewer connection
  • 300 mmperforated storm pipe through a hydro brake

Send your scheme for a price

Goes straight to Haydn Buffham, the director.

Prefer to talk? Call Haydn on 01945 669203.

Client
Rose Homes Ltd
Location
Newtown Road, Ramsey, Cambridgeshire
Scope
Groundworks package for 9 plots: ring beams, foundations, substructure blockwork, block and beam, plot drainage and services, foul and storm drainage
Status
Main contractor on site; returning to complete road surfacing, paths and patios
The brief

A full groundworks package on Newtown Road

Rose Homes is building nine homes on Newtown Road, Ramsey: two pairs of semi-detached homes and five detached units. The brief was the whole groundworks package, from the first dig to the road, with HB Developments as main contractor on site.

That meant excavation for all nine plots, ring beams, concrete foundations, substructure blockwork, block and beam floors, plot drainage and services, foul drainage connected to the road sewer, and a storm water system.

HB Developments groundworker setting a drainage chamber in the trench at Newtown Road, Ramsey, with the excavator above
HB Developments groundworker setting a drainage chamber in the trench at Newtown Road, Ramsey, with the excavator above
The challenge

A 3.5 m deep sewer connection and storm water on Fen-edge ground

The foul drainage had to connect to the road sewer 3.5 m down. A trench that deep is a confined, engineered job: shored, sequenced and dug in the right order so the road and the plots keep moving around it.

Storm water was the other test. We laid 300 mm perforated pipe so water soaks away along the run, flowing through a hydro brake that controls how fast it leaves the site. That is how a new estate stops flooding the street below it.

Photos from the job

Our own photographs from the job.

Plot drainage run with a chamber between two block and beam floors at Ramsey
Plot drainage run with a chamber between two block and beam floors at Ramsey
Deep sewer trench dug along the line of the new road at Ramsey
Deep sewer trench dug along the line of the new road at Ramsey
Excavator loading spoil on the Rose Homes site at Ramsey
Excavator loading spoil on the Rose Homes site at Ramsey
Block and beam floor laid on a plot at Newtown Road, Ramsey
Block and beam floor laid on a plot at Newtown Road, Ramsey
Stoned road formation with service ducts at the Rose Homes site in Ramsey
Stoned road formation with service ducts at the Rose Homes site in Ramsey
Plots at footing stage along the site road on the Ramsey development, with houses behind
Plots at footing stage along the site road on the Ramsey development, with houses behind
Distant aerial view of four plots at foundation stage in a row on the Ramsey development
Distant aerial view of four plots at foundation stage in a row on the Ramsey development
Aerial view of the Ramsey development from the other end, with poured slabs and plot footings
Aerial view of the Ramsey development from the other end, with poured slabs and plot footings
HB Developments operative in branded hi-vis setting a drainage chamber at the Rose Homes site in Ramsey
HB Developments operative in branded hi-vis setting a drainage chamber at the Rose Homes site in Ramsey
What we did

Every plot, every drain, every service

  • Excavated 9 plots: 2 pairs of semis and 5 detached units.
  • Ring beams and concrete foundations.
  • Substructure blockwork and block and beam floors.
  • Plot drainage and services to every home.
  • Foul drainage with a 3.5 m deep road sewer connection.
  • Storm water drainage in 300 mm perforated pipe, flowing through a hydro brake.

The road at Ramsey is not finished yet. We are returning to complete the road surfacing, paths and patios. More on how we run roads and sewers and drainage.

Wrapped perforated storm pipe running to a large chamber ring on the Ramsey site
Wrapped perforated storm pipe running to a large chamber ring on the Ramsey site
The outcome

Main contractor, start to finish

Rose Homes has one contractor carrying the site: the groundworks gang, the drainage, the services and the road all run by HB Developments. No gaps between packages, no finger pointing between trades, one programme.

If you are a developer with a scheme in Cambridgeshire or anywhere in the country, send the drawings through the form and Haydn will price the package, or the whole site as main contractor.

The package

The Ramsey package

01

9 plots excavated

2 pairs of semis and 5 detached units.

02

Ring beams and foundations

Concrete foundations under every plot.

03

Substructure

Blockwork and block and beam floors.

04

Foul drainage

3.5 m deep road sewer connection.

05

Storm water

300 mm perforated pipe through a hydro brake.

06

Still to come

Road surfacing, paths and patios, as main contractor.

Reviews

What customers say about Haydn and the team

“Just OUTSTANDING from start to finish, nothing was too much trouble and communication was fantastic throughout the process would absolutely recommend him.”
Marc MatthewsRecommends HB Developments on Facebook, October 2024
“Competitive rates,would highly recommend. I’ve had many jobs done, all been completed to 100% satisfaction.”
George WrightRecommends HB Developments on Facebook, February 2024
“Excellent service fast and efficient 💪”
Tom WrightRecommends HB Developments on Facebook, January 2024
Questions

About this job

Anything else, ring Haydn on 01945 669203.

Who is the client at Ramsey?

Rose Homes Ltd. The site is on Newtown Road, Ramsey, and HB Developments is main contractor on site.

Is the Ramsey road finished?

Not yet. We are returning to complete the road surfacing, paths and patios.

How deep was the sewer connection?

The foul drainage connects to the road sewer 3.5 m down.

What is a hydro brake?

A flow control fitted in the storm drainage that limits how fast water leaves the site, so a new estate does not overload the ditch or sewer downstream.

Can you be main contractor on our scheme?

Yes. At Ramsey we carry the whole site for Rose Homes. Send the drawings and plot numbers and Haydn will price it.

Send the drawings, get a priced package

Plot numbers, packages and a start date are enough to begin. Haydn prices it and comes back to you.

Call HaydnGet a price