Groundworks in Ramsey: nine homes for Rose Homes
Groundworks in Ramsey for Rose Homes on Newtown Road: nine plots, made up of two pairs of semis and five detached homes. We excavated every plot, cast the ring beams and concrete foundations, built the substructure blockwork, laid block and beam, and ran the plot drainage, services, foul drainage and storm water. We are main contractor on site.
- 9plots for Rose Homes
- 3.5 mdeep road sewer connection
- 300 mmperforated storm pipe through a hydro brake
- Client
- Rose Homes Ltd
- Location
- Newtown Road, Ramsey, Cambridgeshire
- Scope
- Groundworks package for 9 plots: ring beams, foundations, substructure blockwork, block and beam, plot drainage and services, foul and storm drainage
- Status
- Main contractor on site; returning to complete road surfacing, paths and patios
A full groundworks package on Newtown Road
Rose Homes is building nine homes on Newtown Road, Ramsey: two pairs of semi-detached homes and five detached units. The brief was the whole groundworks package, from the first dig to the road, with HB Developments as main contractor on site.
That meant excavation for all nine plots, ring beams, concrete foundations, substructure blockwork, block and beam floors, plot drainage and services, foul drainage connected to the road sewer, and a storm water system.

A 3.5 m deep sewer connection and storm water on Fen-edge ground
The foul drainage had to connect to the road sewer 3.5 m down. A trench that deep is a confined, engineered job: shored, sequenced and dug in the right order so the road and the plots keep moving around it.
Storm water was the other test. We laid 300 mm perforated pipe so water soaks away along the run, flowing through a hydro brake that controls how fast it leaves the site. That is how a new estate stops flooding the street below it.
On site, stage by stage
Our own photographs from the job.









Every plot, every drain, every service
- Excavated 9 plots: 2 pairs of semis and 5 detached units.
- Ring beams and concrete foundations.
- Substructure blockwork and block and beam floors.
- Plot drainage and services to every home.
- Foul drainage with a 3.5 m deep road sewer connection.
- Storm water drainage in 300 mm perforated pipe, flowing through a hydro brake.
The road at Ramsey is not finished yet. We are returning to complete the road surfacing, paths and patios. More on how we run roads and sewers and drainage.

Main contractor, start to finish
Rose Homes has one contractor carrying the site: the groundworks gang, the drainage, the services and the road all run by HB Developments. No gaps between packages, no finger pointing between trades, one programme.
If you are a developer with a scheme in Cambridgeshire or anywhere in the country, send the drawings through the form and Haydn will price the package, or the whole site as main contractor.
The Ramsey package
9 plots excavated
2 pairs of semis and 5 detached units.
Ring beams and foundations
Concrete foundations under every plot.
Substructure
Blockwork and block and beam floors.
Foul drainage
3.5 m deep road sewer connection.
Storm water
300 mm perforated pipe through a hydro brake.
Still to come
Road surfacing, paths and patios, as main contractor.
More of our jobs
Real jobs, named places, our own photos.

Six new builds for Ark Property and MDG
Foundations up to 2.9 m wide, 600 m³ of concrete poured and 4,000 tonnes mucked away.
See the job
Bourne Town Hall for Probus
Heritage groundworks: dig to formation with an archaeologist, foam glass, new drainage and time capsules, on time and in budget.
See the job
Piled plots and a new drainage board drain
Four plots piled including design, a new drainage board drain cut and shaped, and two new culverts.
See the jobWhat customers say about Haydn and the team
“Just OUTSTANDING from start to finish, nothing was too much trouble and communication was fantastic throughout the process would absolutely recommend him.”
“Competitive rates,would highly recommend. I’ve had many jobs done, all been completed to 100% satisfaction.”
“Excellent service fast and efficient 💪”
About this job
Anything else, ring Haydn on 01945 669203.
Who is the client at Ramsey?
Rose Homes Ltd. The site is on Newtown Road, Ramsey, and HB Developments is main contractor on site.
Is the Ramsey road finished?
Not yet. We are returning to complete the road surfacing, paths and patios.
How deep was the sewer connection?
The foul drainage connects to the road sewer 3.5 m down.
What is a hydro brake?
A flow control fitted in the storm drainage that limits how fast water leaves the site, so a new estate does not overload the ditch or sewer downstream.
Can you be main contractor on our scheme?
Yes. At Ramsey we carry the whole site for Rose Homes. Send the drawings and plot numbers and Haydn will price it.
Send the drawings, get a priced package
Plot numbers, packages and a start date are enough to begin. Haydn prices it and comes back to you.