
House foundations and footings, dug and poured right first time
House foundations decide everything above them. HB Developments digs, steel fixes and pours footings across the Fens, Lincolnshire, Cambridgeshire and Norfolk, then takes the plot up to DPC, oversite or block and beam. We built our own bungalow at Walpole St Peter on 2 m deep footings.
- 2 mdeep footings at Walpole St Peter
- 80 m³of concrete pumped in
- 600 tof soil off site in a week
Foundation contractors who build on the ground they dig
Most foundation contractors hand you a trench and leave. We build homes ourselves, so we dig footings the way a builder needs them: square, level, to the depth the engineer and building control sign off, and clean enough for the pour to go in the same day.
On our own bungalow at Walpole St Peter the ground demanded 2 m deep footings. The team dug them in relentless rain, took 600 tonnes of soil off site and pumped 80 m³ of concrete in a single week. That is the standard on every plot, whether it is your house or ours.
Footings: from string lines to concrete
Every set of footings follows the same sequence, and every step is checked before the next one starts.
- Set out. Pegs and string lines from your drawings, so the walls land exactly where the architect drew them.
- Dig. Our own excavators take the trench to formation, and the spoil goes straight onto a lorry or into a heap for reuse.
- Inspect. Building control sees the open trench. On soft or mixed ground we go deeper, or switch to piled foundations.
- Steel. Where the design calls for it, reinforcement cages are fixed in the trench and checked before the pour.
- Pour. Ready-mix straight from the wagon, or pumped where the lorry cannot reach.
We fixed the steel cages for the new builds we did in Spalding for Ringwood and Simpson, so reinforced footings are routine work for our gangs.

On site, stage by stage
Our own photographs from the job.



Oversite concrete and block and beam floors
Footings are only half the substructure. We build the blockwork up to DPC, then finish the ground floor one of two ways.
- Oversite concrete. Stone, blinding, membrane and a poured slab. At Gedney Hill we dug and poured the footings, then stoned and poured the oversite and set the kerbs.
- Block and beam. Precast beams laid across the walls and infilled with blocks. It goes down fast and suits a ventilated void. On Plot 1 at Weston Hills, block and beam and drainage were done in one push, all stoned up and ready for the bricklayers.
Either way, you get a level, square deck ready for the walls to go up.

One house or a whole development
The same gangs dig for homeowners and for developers. On a nine-home site at Ramsey we dug seven plots in the first week, then finished every footing and ring beam with block and beam on four plots ready for drainage. On a six-home scheme at Surfleet we carried the groundworks and the brickwork for Ark Property Centre.
For a single house, a self-build or a replacement dwelling, you get the same plant, the same checks and the same site management. Building an extension rather than a whole house? See foundations for your extension.

What a foundations package includes
Set out
Pegs and string lines from your approved drawings.
Dig and cart away
Our own excavators, with spoil loaded straight onto lorries.
Steel fixing
Reinforcement cages fixed and checked before the pour.
Concrete
Poured from the wagon or pumped where access is tight.
Blockwork to DPC
Our own bricklayers carry the walls up to damp proof course.
Ground floor
Oversite concrete or block and beam, whichever the design calls for.
Jobs that prove it
Real jobs, named places, our own photos.

Internal raft slab for Bespoke Group
A raft slab cast inside a barn.
See the job
Groundworks for a Stamford builder
Footings dug, poured and laid in block.
See the job
High-spec bungalow, our own
2 m deep footings, 80 m³ of concrete and 600 tonnes off site in a week. On the market at £375,000.
See the jobWhat customers say about Haydn and the team
“Just OUTSTANDING from start to finish, nothing was too much trouble and communication was fantastic throughout the process would absolutely recommend him.”
“Competitive rates,would highly recommend. I’ve had many jobs done, all been completed to 100% satisfaction.”
“Excellent service fast and efficient 💪”
Questions we get asked
Anything else, ring Haydn on 01945 669203.
How deep do house foundations need to be?
As deep as the ground demands. Building control decides on site once the trench is open. On firm clay a standard strip footing works. At Walpole St Peter our footings went 2 m deep. Where solid ground sits too far down, piles are the answer.
Do you do the blockwork to DPC as well?
Yes. Our bricklayers take the walls from the footings to DPC and lay the oversite or block and beam, so one firm hands you a finished substructure.
Can you work from my architect's drawings?
Yes. Send them over and Haydn prices the footings, steel, concrete and floor line by line.
What happens to the soil you dig out?
It goes off site on our lorries or stays in a heap for landscaping, whichever you prefer. At Walpole we moved 600 tonnes in a week.
Do you build foundations for developers?
Yes. Ramsey, Surfleet, Papworth Everard and Spalding were all contract groundworks. Developers can send drawings for a price.
How do I get a price?
Book a free site visit. Haydn looks at the ground and the access and prices the job. Or call him on 01945 669203.
Book a free site visit
Tell us about the job. Haydn comes out, looks at the ground and the access, and gives you a price.