Section 38 vs section 278 works explained

Section 38 vs section 278 comes down to one question: is the road new, or is it already public? A section 38 agreement adopts a new estate road. A section 278 agreement lets you alter the existing highway, most often for your site access. Here is how each works and what the groundworker builds.

  • 9homes at Ramsey with road drainage complete
  • 6homes at Surfleet with a permeable road
  • NRSWAstreet works qualified

Send your scheme for a price

Goes straight to Haydn Buffham, the director.

Prefer to talk? Call Haydn on 01945 669203.

The short answer

Section 38 and section 278 side by side

Section 38Section 278
The lawHighways Act 1980, section 38Highways Act 1980, section 278
What it coversNew roads built by the developer, adopted as public highwayAlterations to the existing public highway
Typical worksEstate roads, footways, road drainage, street lightingBellmouths, junctions, footway links, crossings, visibility splays
Where the work happensOn the development landOn a live public road
Why you need itSo the council maintains the road, not a management companyUsually a planning condition or obligation for the access
SecurityBond or cash deposit until adoptionBond or cash deposit until the works are signed off
Who signsDeveloper and the highway authorityDeveloper and the highway authority

The highway authority is the county or unitary council. Around our base that means Cambridgeshire, Lincolnshire and Norfolk County Councils, each with its own design guide and specification.

New roads

Section 38: new estate roads adopted by the council

A section 38 agreement is a deal with the highway authority: you build the new road to its standard, it inspects the work, and after a maintenance period it adopts the road as a public highway maintainable at public expense.

The usual sequence runs like this. The road is designed to the council's estate road standards and submitted for technical approval. The agreement is signed and a bond or cash deposit lodged, along with the council's inspection fees. The developer builds the road with inspections at each layer. Once the road is substantially complete a first certificate starts the maintenance period, during which the developer puts right any defects. After a final inspection the road is adopted and the bond released.

Building plots on a private street triggers the Advance Payments Code, which asks the developer to secure the cost of the street works before building starts. A section 38 agreement with its bond is the usual way to meet that. The alternative is a private road kept by a management company, which buyers and lenders look at closely.

The existing road

Section 278: works on the existing public highway

Section 278 works are the ones outside your red line: the new bellmouth where the estate road meets the existing road, a widened junction, a footway link to the village, a dropped crossing, a pedestrian refuge or a visibility splay cut back. The planning permission requires them before occupation.

The council approves the design, normally after a road safety audit, and the developer pays for the works and lodges security. Because the work sits on a live road, it is street works: permits, traffic management, signing and guarding, and qualified operatives under the New Roads and Street Works Act 1991 (NRSWA).

That is where a contractor's tickets matter. HB Developments holds street works (NRSWA) qualifications, so we open, build and reinstate the highway ourselves rather than handing the junction to another firm.

Ducting laid in a trench behind red barriers on the Holbeach utilities job
Ducting laid in a trench behind red barriers on the Holbeach utilities job
On a real site

Where section 38, section 278 and section 104 meet

On a typical small residential scheme all three agreements touch the same few metres of ground. The section 278 works form the access off the existing road. The section 38 estate road runs from that junction into the site. Under the road, the foul and surface water sewers are built for adoption under a section 104 agreement with the water company, while the gullies and carrier drains serving only the road go with the road.

Sequence is everything. Sewers and ducts go in before the road build-up. The road is taken to base course early so plots can be reached and serviced, and the surface course goes down at the end, once the heavy plant and scaffold have gone, so it is not damaged during the build.

That is how our Ramsey site ran: all road drainage and plot groundworks completed for the nine homes, the site handed to the bricklayers, then our return as main contractor to complete the road surfacing, paths and patios. At Surfleet we laid the permeable road serving Plots 1 and 2 for Ark Property Centre.

Aerial view of the Ramsey development with plots at footings and block and beam and two poured slabs
Aerial view of the Ramsey development with plots at footings and block and beam and two poured slabs
What we build

What the groundworks contractor builds on S38 and S278 works

  • Setting out to the approved highways drawings, with levels checked against the drainage
  • Excavation to formation, with soft spots dug out and replaced
  • Road drainage: gullies, carrier drains and connections
  • Service ducts and crossings laid before the road build-up
  • Sub-base laid and compacted in layers, ready for each inspection
  • Kerbs, edgings and footways
  • Base course early, surface course at the end, or permeable block paving where the design calls for it
  • Junction works on the live road with traffic management and reinstatement

Pricing the roads with the sewers and the plots keeps one programme. See our S38 and S278 road works service.

Avoid delays

Where S38 and S278 schemes lose time

Most hold-ups on small schemes come from paperwork and sequencing, not from the build itself:

  • Late technical approval. The council cannot inspect a road it has not approved, so layers built early are at the developer's risk.
  • Missed inspections. Each layer is inspected before the next goes on. Book them and have the layer ready, or the gang stands.
  • Drainage clashes. Road gullies, sewers and service ducts fighting for the same space. Check the drainage and highways drawings against each other before the first dig.
  • Surface course too early. Laid before the plots are finished, it gets damaged by plant and has to be patched before adoption.
  • Street works permits. Work on the live road needs a permit and traffic management booked ahead, so the S278 junction belongs in the programme from day one.
The package

Send these with your road works tender

01

Highways layout

The approved or submitted S38 and S278 drawings, with levels and construction details.

02

Council specification

The highway authority's build-ups and materials set the quantities we price.

03

Drainage layout

Road drainage and sewers are programmed together, so we need both.

04

Planning conditions

The condition wording tells us when the access and the S278 works must be finished.

05

Phasing

Which plots come first decides when base course and surface course go down.

Reviews

What customers say about Haydn and the team

“Just OUTSTANDING from start to finish, nothing was too much trouble and communication was fantastic throughout the process would absolutely recommend him.”
Marc MatthewsRecommends HB Developments on Facebook, October 2024
“Competitive rates,would highly recommend. I’ve had many jobs done, all been completed to 100% satisfaction.”
George WrightRecommends HB Developments on Facebook, February 2024
“Excellent service fast and efficient 💪”
Tom WrightRecommends HB Developments on Facebook, January 2024
Questions

Quick answers

Anything else, ring Haydn on 01945 669203.

What is the difference between section 38 and section 278?

Section 38 covers new roads a developer builds for the council to adopt. Section 278 covers works the developer carries out on the existing public highway, such as a new junction or footway link.

Do I need both on one site?

Often, yes. A new estate road for adoption needs a section 38 agreement, and the junction where it meets the existing road needs section 278 works.

Who builds section 278 works?

The developer's contractor, approved by the highway authority. The work is on a live road, so the operatives need street works (NRSWA) qualifications, which we hold.

Why is the surface course laid last?

So it is not damaged by plant, deliveries and scaffold during the build. The road runs on base course until the plots are finished.

Is road drainage part of section 104?

Drains serving only the road go with the road under section 38. Sewers serving the homes are adopted by the water company under section 104.

Can you price the roads, sewers and plots together?

Yes. Send your drawings and Haydn prices each package line by line, so you can award one or all.