Ducting in Holbeach: 180 m for Taylors Bulbs
Ducting in Holbeach for Taylors Bulbs: 180 m of new 125 mm electrical duct, broken out through tarmac and concrete, cat scanned around the existing services including the Holbeach substation supply, then reinstated. The site stayed fully operational the whole time, with lorry access kept open while we crossed the main entrance.
- 180 mof 125 mm electrical duct
- Fullyoperational site throughout
- 125 mmduct with jointing pits
- Client
- Taylors Bulbs Ltd
- Location
- Holbeach, Lincolnshire
- Scope
- 180 m of 125 mm electrical duct, breakout, cat scan, jointing pits, compacted backfill, concrete and tarmac reinstatement
- Outcome
- Completed with the site fully operational and lorry access maintained
New power ducting through a working bulb site
Taylors Bulbs needed 180 m of new 125 mm electrical duct across their Holbeach site. The run crossed tarmac, concrete and the main site entrance, and passed close to the supply for the Holbeach substation.
Live services, a live entrance and a tight timeframe
Health and safety, access and timeframe were the important factors. The site had to stay fully operational, so lorries still needed to get in and out while we were digging across the main entrance. Existing cables and pipes ran under the yard, including the substation supply.
We cat scanned the route to find the existing services and worked carefully around them, then plated the open trench at the entrance so the lorries kept moving.

On site, stage by stage
Our own photographs from the job.





Break out, lay, backfill, reinstate
- Broke out the tarmac and concrete along the route.
- Cat scanned to find the existing services, including the Holbeach substation supply, and dug carefully round them.
- Laid 180 m of 125 mm electrical duct and installed the jointing pits.
- Backfilled with sand and Type 1, compacted in layers.
- Reinstated with concrete and tarmac.
Our operatives hold street works (NRSWA) qualifications. More on sewer connections and utility ducting.

Power in, site never closed
The duct run went in with the site fully operational throughout and lorry access maintained across the main entrance. The surfaces were put back in concrete and tarmac, compacted in layers so they stay level under heavy traffic.
Commercial and agricultural sites cannot stop for groundworks. If yours needs ducting, drainage or commercial concrete while it keeps trading, send us the site plan.
How we run a package like this
Every job starts with the drawings and a conversation with Haydn, the director. He prices the package line by line, agrees the programme with your site manager and stays the point of contact until the last load leaves site. Our sites run under SMSTS site management, every employee carries a CSCS card, every plant operator holds the relevant tickets, and we carry £10 million of insurance through First Point.
Send the drawings through the form at the top of this page, or call Haydn, and you will have a priced package back with a start date.
The Taylors Bulbs job
180 m of duct
125 mm electrical duct across the site.
Cat scanned
Existing services found and worked around.
Jointing pits
Installed along the run.
Compacted backfill
Sand and Type 1 in layers.
Reinstated
Concrete and tarmac put back.
Site kept open
Lorry access maintained across the main entrance.
More of our jobs
Real jobs, named places, our own photos.

Bourne Town Hall for Probus
Heritage groundworks: dig to formation with an archaeologist, foam glass, new drainage and time capsules, on time and in budget.
See the job
Yard, bays and wash bay
Commercial concrete for RJ Wright Ltd.
See the job
Grain store floors and aprons
Agricultural concrete floors and brush-finish aprons.
See the jobWhat customers say about Haydn and the team
“Just OUTSTANDING from start to finish, nothing was too much trouble and communication was fantastic throughout the process would absolutely recommend him.”
“Competitive rates,would highly recommend. I’ve had many jobs done, all been completed to 100% satisfaction.”
“Excellent service fast and efficient 💪”
About this job
Anything else, ring Haydn on 01945 669203.
Who was the client in Holbeach?
Taylors Bulbs Ltd. We laid 180 m of new 125 mm electrical duct across their site.
Did the site have to close?
No. The site remained fully operational, with access for lorries kept open while we crossed the main entrance.
How do you avoid existing cables and pipes?
We cat scan the route first, mark what is found and dig carefully round it. At Taylors Bulbs that included the Holbeach substation supply.
How do you reinstate a trench in a yard?
Backfill with sand and Type 1 compacted in layers, then concrete and tarmac on top, so the surface stays level under lorries.
Are you street works qualified?
Yes. Our operatives hold street works (NRSWA) qualifications.
Send the drawings, get a priced package
Plot numbers, packages and a start date are enough to begin. Haydn prices it and comes back to you.