Our own development

Two new build bungalows at Weston Hills, both sold off plan

Two new build bungalows at Weston Hills, on Broadgate near Spalding, built by HB Developments from the first footing to the last fence panel. Plot 2 went onto piles and a ring beam. Both bungalows sold off plan, before either one was finished.

  • 23-bed executive bungalows
  • 2 of 2sold off plan
  • 6 monthsfrom foundations to completion

Get a free site visit

Haydn calls you back, looks at the ground and prices the job.

Or call Haydn on 01945 669203.

Place
Broadgate, Weston Hills, Spalding PE12
Client
Our own development
Scope
Two new build bungalows: groundworks, piles and ring beam on Plot 2, block and beam, drainage, brickwork, finishing, fencing and drives
Dates
October 2023 to August 2025
Planning
H22-0931-23
Result
Both bungalows sold off plan
The job

Our own two-plot development at Broadgate

Weston Hills was our money and our risk. We secured two plots on Broadgate, Spalding PE12 (planning reference H22-0931-23), and built two detached bungalows for sale. We announced the scheme in October 2023 and interest was high before a spade went in.

Work started on site in early December 2023, and we made good progress despite the bad weather. Both plots went on Rightmove while they were still under construction, and both sold off plan.

Weston Hills site start from the air: strip footings poured in the plot outlines with a mini excavator and telehandler
Weston Hills site start from the air: strip footings poured in the plot outlines with a mini excavator and telehandler
Plot 1

Footings to wind and watertight in under four months

Plot 1 moved fast because one team ran the groundworks and handed straight over to the bricklayers:

  • December 2023: footings, block and beam and drainage complete by 28 December, stoned up, with materials on site so the bricklayers could push on in the new year.
  • January 2024: first lift scaffold up in the second week. The bricklayers battled the weather to get to wall plate, then AJB Group Carpentry put the roof on and the brickies came back for the gables.
  • March 2024: wind and watertight, ready for underfloor heating and screed the following week.
Photos from the job

Our own photographs from the job.

Drone view of Plot 2 at Weston Hills dug out, with excavators beside the finished Plot 1 bungalow
Drone view of Plot 2 at Weston Hills dug out, with excavators beside the finished Plot 1 bungalow
Drone view of both finished Weston Hills bungalows with gravel drives, gardens and fields behind
Drone view of both finished Weston Hills bungalows with gravel drives, gardens and fields behind
Garden side of the finished Plot 1 bungalow at Weston Hills with glazed doors and a new lawn
Garden side of the finished Plot 1 bungalow at Weston Hills with glazed doors and a new lawn
Grey shaker kitchen with a white island inside the finished Plot 1 bungalow at Weston Hills
Grey shaker kitchen with a white island inside the finished Plot 1 bungalow at Weston Hills
Open-plan living space with roof lights and garden doors in the Plot 2 bungalow at Weston Hills
Open-plan living space with roof lights and garden doors in the Plot 2 bungalow at Weston Hills
Drone view over the striped lawn and new fencing of Plot 1 at Weston Hills
Drone view over the striped lawn and new fencing of Plot 1 at Weston Hills
Drone view of a finished HB Developments bungalow at Weston Hills from the garden side, with a porcelain patio and new fencing
Drone view of a finished HB Developments bungalow at Weston Hills from the garden side, with a porcelain patio and new fencing
Both finished Weston Hills bungalows front on, with a block-paved entrance
Both finished Weston Hills bungalows front on, with a block-paved entrance
HB Developments Building and Groundworks site board outside the Weston Hills bungalows
HB Developments Building and Groundworks site board outside the Weston Hills bungalows
Plot 1

Plastered, fenced, finished and sold

By early May 2024 the external finishing was well under way and Eastern Construction Consultants had the bungalow fully plastered out, ready for second fix. In October 2024 we finished the external fencing, drive and kerbs. Plot 1 was complete and sold by November 2024.

The finish is the part buyers see: a porcelain patio, bi-fold doors and a new lawn at the back, close-board fencing all round.

Rear of the finished Plot 1 bungalow at Weston Hills with a porcelain patio, bi-fold doors and new lawn
Rear of the finished Plot 1 bungalow at Weston Hills with a porcelain patio, bi-fold doors and new lawn
Plot 2

Piles cropped and a ring beam before the weather turned

Plot 2 went onto a piled foundation. In November 2024 we dug out the plot and cropped the piles, so the ring beam could go in and the concrete could be poured before the winter weather arrived. By 25 November Plot 2 was dug out and concreted, ready to continue in the new year.

On a piled foundation the piles carry the load down past soft ground to firmer strata. Each pile is cropped to level, the steel is tied in, and a reinforced ring beam is cast across the pile heads to carry the walls. On Fen ground that is often the difference between a house that stays put and one that moves. Read more on our piled foundations page, or compare the options in piled vs strip foundations.

Cropped piles and ring beam on Weston Hills Plot 2 with a groundworker on site
Cropped piles and ring beam on Weston Hills Plot 2 with a groundworker on site
Plot 2

Trusses, windows and sold early in the build

Plot 2 came to market in January 2025. The roof trusses were on by early March, and in April we reported the bungalow sold in the early stages of the build, with the windows in and external finishing starting the next week. We completed Plot 2 in August 2025. Both plots sold off plan.

Aerial view of Weston Hills Plot 2 at roof truss stage under scaffold, beside the finished Plot 1 bungalow
Aerial view of Weston Hills Plot 2 at roof truss stage under scaffold, beside the finished Plot 1 bungalow
What it proves

What it means if you are building near Spalding

When we build for ourselves, nobody signs off our corners but us. The same team, the same piling method and the same finishing standard go onto your plot. If you are planning a self-build or a new home anywhere around Spalding, Haydn will walk the site with you for free and tell you straight what the ground needs.

Want to buy one of ours instead? See our developments.

Built in six months

Sold off plan and completed within 6 months

Both homes are 3-bed executive bungalows, completed by our team of in-house tradespeople and trusted subcontractors. Both were built to a high specification, including quartz worktops, both sold off plan, and both were completed within 6 months of starting on the foundations.

That pace comes from owning the plant and running the gangs ourselves. See what is for sale and coming soon.

Kitchen island with quartz worktop in a finished Weston Hills bungalow
Kitchen island with quartz worktop in a finished Weston Hills bungalow
Reviews

What customers say about Haydn and the team

“Just OUTSTANDING from start to finish, nothing was too much trouble and communication was fantastic throughout the process would absolutely recommend him.”
Marc MatthewsRecommends HB Developments on Facebook, October 2024
“Competitive rates,would highly recommend. I’ve had many jobs done, all been completed to 100% satisfaction.”
George WrightRecommends HB Developments on Facebook, February 2024
“Excellent service fast and efficient 💪”
Tom WrightRecommends HB Developments on Facebook, January 2024
Questions

About this job

Anything else, ring Haydn on 01945 669203.

Are the Weston Hills bungalows still for sale?

No. Both sold off plan. Our current site is three new homes at Wyberton, Boston, priced from £275,000.

What is a pile and ring beam foundation?

Piles are driven or bored down to firm ground, cropped to level, then tied together by a reinforced concrete ring beam that carries the walls. It is the standard answer on soft Fen and peat ground. See piled foundations.

How long did Plot 1 take?

Work started in December 2023. Plot 1 was wind and watertight in March 2024, and finished and sold by November 2024.

Did HB Developments do all the work?

We ran the groundworks, drainage, block and beam, external works and the whole build programme. AJB Group Carpentry fitted the roof and Eastern Construction Consultants did the plastering, both trusted partners we use on our own sites.

Can you build a bungalow like this on my plot?

Yes. Tell us about your plot and Haydn will arrange a free site visit. Call 01945 669203.

Book a free site visit

Tell us about the job. Haydn comes out, looks at the ground and the access, and gives you a price.

Call HaydnGet a price